Bridge Updates

Update 1-30-17

Bridge repairs are hoped to be completed by the first week of February. Crews working to install safety railings and new fencing


Update 12-19-16

The Steel Fabricator will be erecting the beams for the pedestrian bridge tomorrow, 12/19/16. The crane will be arriving on site between 6:30 – 7:00 AM. The steel installer cannot move their equipment between 7:00 – 9:00 AM to allow for student traffic. The crane should be out of the site before classes conclude, or between 12:00 and 2:00 PM.

Update 12-8-16
Substantial Completion Date is January 17, 2017.

 

Update 11-14-2016

Steel shop drawings were approved on 11/7 – takes about 30 days to get the steel so still starting demolition beginning of December.

Construction should be about a month and then punch list.  So everything should be complete by end of January.